Industrial Wastewater Treatment System Phase I Improvements

  • Client:Lincoln Industries
  • Location:Lincoln, Nebraska
  • Contract Amount:$557,000
  • Contract Type:Design-Build
  • Engineer:Burns & McDonnell

​CAS was hired by Burns & McDonnell Engineering to perform construction services on their Design-Build project for Lincoln Industries, a private company that provides chrome plating of parts for multiple industries.  CAS performed the concrete, mechanical and steel frame erection. 

The project consisted of updating Lincoln Industries' complex chemical cleaning and disposal system.  Working in the middle of their indoor existing plant, CAS demoed the existing process plant, retrofitted old in-ground concrete tanks to become containment areas, installed 6 new RFP tanks, erected a new steel frame for the pumping systems and installed the complete mechanical process equipment and piping. 

Access to the work area was very confined and CAS consistently coordinated with the Owner to assure that the overall plant operations were not affected by this project